The construction of the Patimban Access Toll Road continues to make significant progress as one of Indonesia's National Strategic Projects (PSN), serving as a key pillar in strengthening logistics connectivity across West Java.
The 37.05-kilometer toll road is expected to significantly reduce travel time to Patimban Port, lower national logistics costs, and stimulate economic growth and investment throughout West Java's industrial corridors.
Erwin Herlambang Kuncoro Putra, Commitment-Making Officer (PPK) for Highway Project (JBH) 2 of West Java Province, explained that the Patimban Access Toll Road is a dedicated transport corridor connecting the Cipali Toll Road, part of the Trans-Java Toll Road network, with Patimban International Port.
"The Patimban Access Toll Road is one of the National Strategic Projects designed to connect the Cipali Toll Road with Patimban International Port through a dedicated road network," Erwin said during an interview at his office in Subang on Tuesday (June 30, 2026).
According to Erwin, the project is being implemented under a Public-Private Partnership (PPP) scheme. Under this arrangement, the government is responsible for constructing the section adjacent to Patimban Port, while the connection from the Cipali Toll Road is being developed by PT Jasamarga Akses Patimban as the Toll Road Business Entity (BUJT).
He explained that the BUJT is responsible for constructing approximately 14.11 kilometers of the toll road, while the government is developing the remaining 22.94 kilometers, bringing the total project length to approximately 37.05 kilometers.
Erwin stated that the Patimban Access Toll Road offers several strategic benefits, particularly by improving the efficiency of freight transportation from industrial estates to the port.
The new toll road is expected to shorten travel time between industrial areas and the logistics hub at Patimban Port. With a planned operating speed of approximately 100 kilometers per hour, the journey is projected to take only around 23 minutes.
Besides reducing travel time, the improved efficiency is expected to lower national logistics costs, making the distribution of goods more competitive.
"Our expectation is that logistics costs will decline as distribution becomes faster and more efficient," he said.
Furthermore, Erwin noted that the Patimban Access Toll Road will strengthen export activities from major industrial hubs in West Java, including Cikarang, Cibitung, and Karawang.
Currently, most logistics traffic from these industrial areas depends heavily on Tanjung Priok Port. Once the Patimban Access Toll Road becomes operational, freight distribution is expected to be more evenly distributed.
"One of the primary objectives is to distribute logistics traffic more evenly so that it is no longer concentrated solely at Tanjung Priok Port," Erwin explained.
According to him, the redistribution of logistics traffic will not only reduce congestion at Tanjung Priok Port but also improve the efficiency of Indonesia's national supply chain.
In addition, Patimban Port is projected to become one of West Java's new economic growth centers, making the toll road an essential supporting infrastructure for industrial and commercial activities.
"Patimban Port will become a highly important logistics hub for West Java," he added.
The construction of the Patimban Access Toll Road has been divided into several work packages. The Toll Road Business Entity is responsible for two construction packages, while the government's 22.94-kilometer section has been divided into four packages: Package 1, Package 2, Package 3, and Package 4.
Erwin explained that construction on the BUJT section commenced in the first quarter of 2026 and, according to the contract, is scheduled for completion in the second quarter of 2027.
Meanwhile, construction of the government-managed sections began at different times. Packages 1 to 3 started in the first quarter of 2024, while Package 4 commenced earlier in the fourth quarter of 2023.
Each package was initially scheduled for approximately 700 calendar days. However, following the latest contract amendment through an Extension of Time (EOT), the completion schedule has been adjusted.
"Packages 1 through 3 are targeted for completion in the fourth quarter of 2026, or by the end of December 2026, while Package 4 is expected to be completed in March 2027," Erwin said.
He explained that delays in completing Package 4 were caused by land acquisition issues around the interchange connecting to Patimban Port.
"The delay is due to land acquisition constraints in the interchange area leading to the port," he said.
Nevertheless, Erwin acknowledged that the project schedule remains under continuous evaluation, as several factors—including land acquisition, construction material availability, weather conditions, and on-site implementation challenges—may affect the overall timeline.
Should these critical issues remain unresolved, project completion could be extended until approximately September 2027.
As of June 28, 2026, physical construction progress on the government's 22.94-kilometer section had reached 69.131%.
Erwin said that current construction activities are focused on completing major structures such as bridges and overpasses, drainage systems, roadbed preparation, and earthworks at priority locations.
Acceleration efforts are also concentrated on activities along the project's critical path, particularly embankment works using the preloading method to maintain the overall construction schedule.
According to him, construction acceleration is being supported through resource optimization, the deployment of additional heavy equipment, and the implementation of more adaptive construction methods to improve efficiency while maintaining construction quality and occupational safety.
Construction of each package is being carried out by the following national contractors:
- Package 1: PT Pembangunan Perumahan (Persero) Tbk.
- Package 2: Waskita–Abipraya Joint Operation.
- Package 3: Hutama Karya–Jaya Konstruksi Joint Operation.
- Package 4: WIKA–Adhi Joint Operation.
Project supervision is being conducted under a dedicated supervision contract involving Japan-based Oriental Consultants Global (OCG) in collaboration with several local consulting firms.
With construction progressing steadily, the Patimban Access Toll Road is expected to become a primary national logistics corridor, enhance the competitiveness of West Java's industrial zones, and support the optimization of Patimban Port as one of Indonesia's emerging export-import gateways, generating long-term benefits for businesses and communities across West Java.