Built since 2018, this National Strategic Project during the reign of President Joko Widodo (Jokowi) reached an investment cost of around IDR 43.2 trillion.
Indonesia is indeed one of the countries that has many ports, one of which is Tanjung Priok, Tanjung Perak and Soekarno-Hatta.
Now this time there is one port that is classified as having a very large land area of up to hundreds of hectares.
The port is the Patimban port located in Subang, West Java. With a budget investment of Rp43.2 trillion.
The urgency of the construction of Patimban port is to reduce the volume of shipments to Tanjung Priok port.
Because the Tanjung Priok port location is already difficult to expand again, so that with the Patimban port it is expected to reduce logistics costs between Banten, DKI Jakarta, West Java and Central Java.
It is known that the Patimban port development project, Subang, West Java phase 1-2 with an investment value of up to IDR 9.5 trillion.
Phase 1 (packages 1-4) is 35 hectares, a Container Terminal with a capacity of 250,000 TEUs. And 25 hectares of Vehicle Terminal with a capacity of 218,000 CBUs. The target has been achieved one hundred percent.
The advanced phase of Patimban port development is carried out in phases 1 and 2 from 2022 to 2024 with an investment value of Rp9.5 trillion.
This phase is divided into two packages, namely packages 5 and 6. Package 5 will build a vehicle terminal and package 6 will build a container terminal.
The port with an area of 639 hectares and a capacity of 2.74 million TEUs makes Patimban port one of the largest ports in Indonesia.
It is estimated that the construction of Patimban port will be fully completed by 2027 and its capacity will increase to 7.5 million TEUs.
This is the information about Patimban port, one of the National Strategic Projects (PSN) with an investment cost of Rp43.2 trillion.